I built a 3900 square foot colonial in only 53 hours and 54 minutes. I have also built a 5800 square foot colonial in 110 hours. But don’t expect that kind of time unless ABC Extreme Makeover Home Edition shows up on your job site.

The facts are that building a new home here in Birmingham Michigan are challenging for many reason. First and foremost is weather. But what you should expect is the following
A home between 1500 Square feet to 3000: It should take from start of basement to completions 4 to 5 months in spring or summer. Add a month if you home is started in November, December, January or February.
Homes Between 3000 and 4500 square feet: You will need to add a month in addition for the extra size.
Homes between 4500 and 6500 square feet: You will need to add a month in addition for the extra size.
Homes between 6500 and 9500 square feet: You will need to add a month in addition for the extra size.
These time frames are based on the following condition
- That the proper planning has been done by the customer as far as selection
- Not many field changes after construction has been started.
- And last as long as we do not have to pull out Noel Ark, everything she go as planned.
Like the old saying goes – “Good Preparation makes for good execution”
Remember, greatness in is the details. It is those small details that will make the difference. Most homes in Birmingham Michigan will have those small details. So don’t forget them. Good luck with your search of that new home. I hope this article will help you.
Live Well Custom Homes have 4 New Homes for Sale in Birmingham Michigan ready for you. Please visit our web site under homes New Homes to view what we have. If you do not find what you are looking for , we can help find you that perfect vacant lot in Birmingham , than design and build you a brand new custom home just for you.